A sample of projects relating to wastewater collection and treatment facilities.
Butler, Alabama [2010]
Chlorination System ~ Wastewater Treatment Facility
Engineering Design and Construction Observation
Installation of a concrete chlorine contact tank and connecting piping; including liquid feed chlorination/dechlorination system
Construction Cost: $125,340
Elba, Alabama [2010]
Sewage Pumping Stations Floodproofing
Engineering Design and Construction Observation
Installation of new submersible pumps in 4 sewage pumping stations; construction of 2 fabricated metal elevated platforms; installation of 4 natural gas generators and automatic transfer switches; motor control centers
Funded by FEMA Grant – Construction Cost: $752,850
Florala, Alabama [2010]
Sanitary Sewer System Rehabilitation
Engineering Design and Construction Observation
Installation of 3,000 L.F. of 8” Sanitary Sewer Cleaning/CIPP Liner
Funded by CDBG Grant: Estimated Construction Cost: $291,000
Monroeville, Alabama [2009]
Sanitary Sewer Improvements ~ Phase II (Leslie, Lazenby, & Hwy 41)
Engineering Design and Construction Observation
Installation of 5,550 linear feet of 6”, 8”, & 12” CIP Pipe Lining
Estimated Construction Cost: $315,000
Camden, Alabama [2009]
Sewer System Improvements
Engineering Design and Construction Observation
3,800 L.F. of CIPP gravity sewer, 2 Mechanical Bar Screens, 2 UV Systems Funded by CDBG Grant – Estimated Construction Cost: $446,000
New Brockton, Alabama [2009]
Sewer System Improvements
Engineering Design and Construction Observation
Upgrade of the existing aeration system and construction of a new circular clarifier
Funded by SRF Loan – Estimated Construction Cost: $236,000